Coordinating fire safety directions for the same building

In an older mixed-use building, escape routes, fire-resisting construction and fire service installations can appear in directions from different authorities. Use one location plan for coordination while tracking the status of each direction separately.

Open shop model viewed from above, with a low timber counter, clear floor space, a rear doorway and a miniature red extinguisher.
An open shop model shows how the position of a counter affects the space around it and the approach to a doorway.

Index each direction under its issuing authority

Copy the issuing department, file reference, recipient, date, compliance deadline and attachments from each direction. For composite and domestic buildings under the Fire Safety (Buildings) Ordinance, the Buildings Department deals with fire safety construction improvements and the Fire Services Department deals with fire service installations and equipment. Identify the common area, shop or residential part affected by each item. Keep the original wording in the meeting file.

A stair may appear in both sets of papers, perhaps for a fire-rated door and for an installation. Ask the professional team to mark the respective item references on one floor plan and identify the authority to which each response goes. The committee can then discuss the space together and keep separate records of the replies.

Look at the occupied stair as a whole

Residents, shop deliveries and door swings on adjoining landings all matter to the sequence. Ask the consultant to identify each door, the stair or street side, nearby service enclosures and other common installations. Note which design decisions affect escape or fire-resisting construction. The leaf, frame, closer and surrounding finishes may belong to different trades. Their interfaces belong on the same coordination detail.

Supply the design team with the building’s occupied hours and any access arrangements needed by residents who require assistance. Ask for a phased plan that maintains safe passage and identifies conditions requiring work to pause. The resident notice should name the floor, time, available entrance and contact who can deal with a problem while the work is taking place.

Connect a proposed roof tank with the building design

Suppose the first proposal for the installations includes a roof tank. The owner can establish roof access, the position under consideration and the structural drawings available. Ask who will assess the existing structure, supports, horizontal pipe routes and any associated building work. Allow for future access to maintain the tank and pipework as part of that discussion.

The Buildings Department advises consulting an Authorized Person or Registered Structural Engineer about the structural adequacy of a roof location, with reference to drawings and site verification. Record a decision such as confirming the support location before fixing equipment dimensions. Where space presents a genuine constraint, have the professional team put a documented alternative to the relevant authority and retain the formal response.

Link completion evidence to a door or installation

Before procurement, ask the professional team for the tests, supplier documents, certificates and site checks expected for each item. For a fire-rated door the Buildings Department highlights the supplier’s statement and relevant test or assessment report. Where door sets differ, the schedule can match each installed position, product and drawing revision to its evidence. A folder of certificates is much easier to use when the manager can start with the number on a particular door.

Follow the installation items under the relevant Fire Services Department direction and professional requirements. File the equipment reference, testing or inspection record, responsible practitioner and outstanding work against that direction. When a corridor door later needs attention, the manager can retrieve the information for the correct block and floor.

End the meeting with the status of each item

Track appointment, submission, physical completion, inspection and a reply from the authority as separate events. For example, the professional may have sent door test information to the Buildings Department and still be awaiting an inspection. Give that item a follow-up date. An installation awaiting materials should have its own expected delivery date and an entry on the effect on occupants.

If the deadline is in doubt, contact the issuing authority early and provide the reasons and supporting material it seeks, such as meeting minutes, tender information or a works programme. File each application and response with its own direction. The incoming manager can then see which item needs design input, which needs an inspection appointment and which decision the owners must make at their next meeting.