Building alongside active studios
Wong records his appointment as project manager from March 2018 to September 2020. The site adjoined an existing workshop near the main block, variety studios and drama studios, while news production continued. The package ran from foundations and superstructure to finishes and building services. His account describes regular walks with safety staff to review housekeeping and the site environment. For the production teams immediately outside the work area, these everyday arrangements mattered.
Following a revised drawing to the trades
When the architect issued a revised drawing, the team logged and reviewed it, then sent it to the relevant subcontractors with a record of issue. Weekly site workshops addressed details where trades met. The architect and consultants confirmed the outcome in writing. Materials and shop drawings also went to the architect for review before construction. The record connected each agreed detail with a drawing revision, the people who had received it and the questions still requiring a response.
Assembling the evidence for occupation
Progress records compared the work on site with the master programme week by week and brought the status of architect’s instructions and material submissions into meetings with the client and consultants. For the occupation permit, the team worked with the architect and engineers on statutory drawings, material test reports, certificates and the Buildings Department inspection. Wong records the permit’s issue on 22 September 2020. The paper trail forms part of the history of the completed extension.