Which buildings the finding covers
The Government confirmed the wider site checks in the Legislative Council on 4 November 2026. The Director of Electrical and Mechanical Services reported the inspection findings on 9 November.
The 720 lifts were installed by one contractor in 11 blocks across two Tenants Purchase Scheme estates and in a further 338 private buildings. EMSD also checked lifts installed by other contractors. By 8 November it had sampled about 900 lifts in 480 buildings in that separate group and found the frame components fitted in every lift sampled.
Match the certificate to the installed assembly
In the first two estates, the contractor had submitted fire-resistance certificates for the landing doors. Inspectors found that components specified for those doorsets were missing. New lifts and lifts that have undergone major alterations go through contractor checks, examination by a registered lift engineer and EMSD re-inspection. While reviewing the system, EMSD widened its on-site sampling to cover items including fire-resisting doorsets.
What to request before handover
Ask the project team to identify the lift and floor on installation photographs and link the frame components to the relevant doorset certificate before finishes conceal them. At handover, ask the registered contractor and engineer how discrepancies were resolved. Keep the use or resumption permit and the record of completed remedial work. If EMSD contacts the building, that file helps the manager tell residents which lift is affected and what has been done.